Sewage BOD and COD, and how big the equalisation tank should be

BOD is the oxygen bacteria need to break down the organic matter in sewage; COD is the oxygen needed to oxidise it chemically, so COD is always higher. Their ratio shows how biodegradable the sewage is. The equalisation tank must store the inflow for the hours the plant is not running: a 16-hour plant needs far more storage than a 24-hour plant.

Technically reviewed by Prashant Dwivedi, Co-Founder & Director ·

BOD and COD

TermWhat it measuresNotes
BOD (biochemical oxygen demand)Oxygen used by bacteria to break down organic matterMeasured over 3 days at 27°C in India. It is the main load the biological tank is sized for.
COD (chemical oxygen demand)Oxygen needed to oxidise the organic matter chemicallyMeasured in a few hours. Includes matter bacteria cannot easily break down, so COD is higher than BOD.
BOD/COD ratioShare of the organic matter that is biodegradableA higher ratio means the waste suits biological treatment; a low ratio points to hard-to-degrade content.

Domestic sewage is generally readily biodegradable, which is why STPs rely on biological treatment. Industrial effluent can have a much lower ratio and may need chemical treatment first (see STP vs ETP).

Engine assumption (NBW practice): when only BOD is known for sewage, the Navbharat Water design engine takes COD = 2 × BOD. For industrial effluent both must be measured. See our design method.

Why running hours change the equalisation tank

Sewage keeps arriving whether or not the plant is running. If the plant runs 24 hours, the equalisation tank only has to smooth out the daily peaks. If it runs fewer hours, the tank must also hold everything that arrives while the plant is off, and the plant treats the day's volume at a higher hourly rate when it runs.

BasisHow the equalisation tank is sized
Book method, 24 h runningFrom the inflow pattern over the day, to even out flow and load (CPHEEO 2013; Metcalf & Eddy).
NBW practice, 16 h runningStorage only: the inflow during the hours the plant is off × 1.5. No treatment credit is taken for the tank.

Worked example: 100 KLD plant running 16 hours

  1. Assumption: daily sewage flow 100 KLD (100 m³ a day).
  2. Assumption: the plant runs 16 hours a day, so it is off for 8 hours.
  3. Assumption: inflow is spread evenly over 24 hours, so about 100 ÷ 24 ≈ 4.2 m³ arrives each hour.
  4. Inflow while the plant is off: 100 × 8 ÷ 24 ≈ 33 m³.
  5. NBW practice factor 1.5: 33 × 1.5 ≈ 50 m³ of equalisation storage.

The same plant designed to run 24 hours has no off-period to store, so its equalisation tank is sized from the peaks in the daily inflow pattern instead. The 16-hour plant also has to treat 100 m³ in 16 hours, about 6.25 m³ an hour, instead of about 4.2 m³ an hour (see KLD meaning).

The example is arithmetic on stated assumptions. Real inflow is not even: more arrives in the morning and evening, which changes the storage needed. The 1.5 factor is NBW practice, not a CPHEEO rule, and is pending engineering sign-off.

Frequently asked questions

Why is COD higher than BOD?

COD measures all the organic matter that can be oxidised chemically, including matter bacteria break down slowly or not at all. BOD counts only what bacteria consume in the test period.

What does the BOD/COD ratio tell you?

How biodegradable the wastewater is. A higher ratio means biological treatment works well; a low ratio suggests hard-to-degrade content that may need chemical or advanced treatment.

How big should the equalisation tank be for a 100 KLD STP?

It depends on the running hours and the inflow pattern. For a plant running 16 hours with inflow spread evenly over the day, the inflow during the 8 off-hours is about 33 m³; Navbharat Water's practice of multiplying by 1.5 gives about 50 m³.

Sources

  1. CPHEEO, Manual on Sewerage and Sewage Treatment Systems, Part A: Engineering, MoHUA, 2013.
  2. Metcalf & Eddy / AECOM, Wastewater Engineering: Treatment and Resource Recovery, 5th ed., McGraw-Hill, 2014.