Sewage treatment plant for a 100-bed hospital

A 100-bed hospital needs a 30 KLD MBBR STP (27.2 KLD computed, rounded up to 30 KLD design flow). Plot about 13 × 15.1 m (196 m²). Power: 8.7 kW connected, about 73 kWh a day. Computed outlet meets NGT 2019 (O.A. 1069/2018) for the parameters computed (BOD, COD, TSS, Total N). Budget: ₹13 L – ₹21 L (typical market range, not an NBW quotation).

Technically reviewed by Prashant Dwivedi, Co-Founder & Director ·

Design summary

ItemValue
Design flow30 KLD
Flow over running hours1.88 m³/h (16 h/day)
Flow averaged over 24 h1.25 m³/h
TechnologyMBBR
Plot (footprint)13 × 15.1 m (196 m²)
Connected load8.7 kW
Operating load4.9 kW
Energy per day73 kWh
Energy per m³2.43 kWh/m³
Blower air (all duty blowers)56 Nm³/h
Design methodNBW practice

Treatment units and sizes

UnitPurposeVolumeSizeSizing basis
Oil and grease trapremoves floating oil and grease1.3 m³1.2 × 1.2 × 0.9 moil and grease trap at the peak inflow
Equalisation tankstores and evens out the inflow15.2 m³2.1 × 2.1 × 3.45 mstores the inflow of the 8 h a day the plant does not run, x 1.5 for peaks; air for mixing only, no treatment credit
MBBR anoxic tankremoves nitrate (denitrification)1.9 m³1.2 × 1.2 × 1.35 manoxic (denitrification), 1 h on the running flow; nitrate recycle 3 x
MBBR tank, 2 stages (sieve baffle)biological treatment: BOD and ammonia removal12.6 m³1.9 × 1.9 × 3.5 mlarger of 6 h on the running flow and the tank for the media needed for BOD + ammonia removal; media 5.0 m3 (39 % fill), 2 stages, fine-bubble air
Tube settler (hopper bottom)settles the biological sludge5.9 m³1.4 × 1.4 × 3 mtube settler, surface loading 0.96 m3/m2/h on the running flow, 3.1 h
Chlorine contact tankdisinfection (chlorine contact)1.4 m³1.2 × 1.2 × 1 mchlorine contact on the running flow
Pressure sand filter, FRP 18x65 inchremoves suspended solidsØ 0.46 m × 1.65 m high1.9 m3/h at 11.4 m/h filtration velocity
Activated carbon filter, FRP 24x72 inchremoves colour, odour and chlorineØ 0.61 m × 1.83 m high1.9 m3/h at 6.4 m/h filtration velocity
Treated water tankstores the treated water10.1 m³1.7 × 1.7 × 3.5 mtreated water storage, about 8 h of average flow
Sludge holding tankholds the excess sludge3.9 m³1.2 × 1.2 × 2.7 mabout 7 days of sludge, air mixed
Twin lobe air blowerair for aeration and mixing56 Nm3/h at 4.45 m water column, 1 working + 1 standby (serves eq, mbbr, sludge)

Tank sizes are length × width × depth; vessel sizes are diameter × height.

Water quality, stage by stage

mg/L, computed.
StageBODCODTSSNH₃-NTotal NOil & grease
Inlet250500250404030
Basket screen (inlet chamber)250500250404030
Oil and grease trap237.5476.5250404012
Equalisation tank237.5476.5250404012
MBBR anoxic tank145.9304.32504017.112
MBBR bioreactor7.343.725018.62.4
Tube settler6.241.73018.62.4
Disinfection6.241.73018.62.4
Pressure sand filter4.738.71518.62.4
Activated carbon filter325.21518.62.4
Outlet325.21518.62.4

Outlet vs NGT 2019 (O.A. 1069/2018)

NGT order 30-04-2019 (STPs). Source: Order dated 30-04-2019, para on STP standards. mg/L.
ParameterLimitComputed outletResult
BOD≤ 103Within limit
COD≤ 5025.2Within limit
TSS≤ 2015Within limit
Total N≤ 108.6Within limit

Design assumptions

  • Raw inlet BOD 250 mg/L
  • Raw inlet COD 500 mg/L
  • Raw inlet TSS 250 mg/L
  • Raw inlet TKN 40 mg/L
  • Raw inlet oil and grease 30 mg/L
  • Design temperature 15–32 °C
  • Checked against: NGT 2019 (O.A. 1069/2018)
  • Plant running 16 hours a day
  • Water demand 340 L per bed per day
  • Demand source: CPHEEO Manual on Sewerage and Sewage Treatment Systems 2013 Part A, Table 3.4 (institutional needs for potable water); NBC 2016 Part 9 Sec. 1 Table 2; CPHEEO Manual on Water Supply and Treatment 1999 ch. 2: hospital incl. laundry, up to 100 beds, 340 L per bed per day (above 100 beds 450 L)
  • Flow basis: 100 beds x 340 L/bed/day x 0.8 to sewer = 27.2 KLD, plant 30 KLD
  • Design flow rule: design flow = computed sewage flow rounded up to the next 5 KLD (minimum 10 KLD)
  • Sewage: sewage = 80 % of water supplied (common design assumption; CPHEEO 2013 cl. 3.5 gives 40-90 %)
  • Inlet quality: typical domestic sewage (CPHEEO 2013), no lab report; COD = 2 x BOD
  • Note: sewage only; laboratory and laundry effluent is an ETP case

Design checks

  • screen type: a channel bar screen reaches only 0.12 m/s at a buildable width: basket screen (10 mm) in a 1 x 1 m inlet chamber instead
  • alkalinity after nitrification (before dosing): short of alkalinity: NaHCO3 dosed to keep pH >= 6.8
  • Sludge transfer pump: delivery velocity (DN15): flow too small for the smallest pipe to reach 0.6 m/s; accept or run the pump on a timer at a higher velocity

Budget

Typical market range (published figures, 2026) — not an NBW quotation

CAPEX, turnkey plant. ±30%. Excludes GST, land, civil building and site work.
CapacitySTP — MBBR
30 KLD₹13 L – ₹21 L
Running cost (O&M) per KL treated: power, chemicals, manpower, sludge and AMC/membranes. Typical market range (published figures, 2026) — not an NBW quotation.
CapacitySTP — MBBR
30 KLD₹18 – 32 per KL

These are published market figures, not Navbharat Water's prices. For our own estimate for your project, request a quote.

What quotes often exclude

  • GST
  • Land and civil building / shed
  • Site work: excavation, piling, dewatering
  • Power connection up to the plant panel
  • Consent (CTE / CTO) fees and liaison
  • Operation and maintenance after commissioning

Check your SPCB consent

The State Pollution Control Board consent (CTE / CTO) for your project sets the outlet limits the plant must meet, which can be stricter than the national norm. Check it before you finalise the design: STP discharge norms explained.

Frequently asked questions

What size of tanks does a STP for a hospital (up to 100 beds) (30 KLD) need?

About 52 m3 of tanks in all: oil and grease trap 1.3 m3; equalisation tank 15.2 m3; mbbr anoxic tank 1.9 m3; mbbr tank 12.6 m3; tube settler (hopper bottom) 5.9 m3; chlorine contact tank 1.4 m3; treated water tank 10.1 m3; sludge holding tank 3.9 m3.

How much space and power does a STP for a hospital (up to 100 beds) (30 KLD) need?

A plot about 13 x 15.1 m including the equipment room; 8.7 kW connected, 4.9 kW running, about 73 kWh a day (2.43 kWh per m3) at 16 h a day.

Does a STP for a hospital (up to 100 beds) (30 KLD) meet NGT 2019?

Computed outlet BOD 3, TSS 15 mg/L against NGT 2019 BOD 10, COD 50, TSS 20 mg/L: within the limits.

Related

Preliminary estimate, not for construction. Detailed design and quotation by NBW engineers.