50 KLD MBR sewage treatment plant: sizes, footprint, power and budget

This 50 KLD MBR sewage treatment plant is sized for 16 hours of running a day. Plot about 12.9 × 14.1 m (182 m²). Power: 15.2 kW connected, about 125 kWh a day. Computed outlet meets NGT 2019 (O.A. 1069/2018) for the parameters computed (BOD, COD, TSS, Total N). Budget: ₹35 L – ₹50 L (typical market range, not an NBW quotation).

Technically reviewed by Prashant Dwivedi, Co-Founder & Director ·

Design summary

ItemValue
Design flow50 KLD
Flow over running hours3.12 m³/h (16 h/day)
Flow averaged over 24 h2.08 m³/h
TechnologyMBR
Plot (footprint)12.9 × 14.1 m (182 m²)
Connected load15.2 kW
Operating load8.2 kW
Energy per day125 kWh
Energy per m³2.5 kWh/m³
Blower air (all duty blowers)183 Nm³/h
Design methodNBW practice

Treatment units and sizes

UnitPurposeVolumeSizeSizing basis
Oil and grease trapremoves floating oil and grease0.7 m³2.6 × 0.3 × 0.9 moil and grease trap at the peak inflow
Equalisation tankstores and evens out the inflow25 m³2.65 × 2.7 × 3.5 mstores the inflow of the 8 h a day the plant does not run, x 1.5 for peaks; air for mixing only, no treatment credit
MBR aerobic / membrane tank (flat sheet)biological treatment and membrane filtration12.6 m³1.9 × 1.9 × 3.5 mmembrane tank: 160 m2 flat-sheet membrane, net flux 19.5 L/m2/h, 4.0 h aerobic
MBR anoxic tankremoves nitrate (denitrification)3.2 m³0.95 × 0.95 × 3.5 manoxic (denitrification) on the running flow
Chlorine contact tankdisinfection (chlorine contact)1.6 m³1.15 × 0.4 × 3.5 mchlorine contact on the running flow
Treated water tankstores the treated water16.9 m³2.2 × 2.2 × 3.5 mtreated water storage, about 8 h of average flow
Sludge holding tankholds the excess sludge4.4 m³1.1 × 1.15 × 3.5 mabout 7 days of sludge, air mixed
Twin lobe air blowerair for aeration and mixing183 Nm3/h at 4.5 m water column, 1 working + 1 standby (serves eq, mbr, mbr, sludge)

Tank sizes are length × width × depth; vessel sizes are diameter × height.

Water quality, stage by stage

mg/L, computed.
StageBODCODTSSNH₃-NTotal NOil & grease
Inlet250500250404030
Basket screen (inlet chamber)250500250404030
Oil and grease trap237.5476.5250404012
Equalisation tank237.5476.5250404012
Membrane bioreactor (MBR)4.838.92182.4
Disinfection4.838.92182.4
Outlet4.838.92182.4

Outlet vs NGT 2019 (O.A. 1069/2018)

NGT order 30-04-2019 (STPs). Source: Order dated 30-04-2019, para on STP standards. mg/L.
ParameterLimitComputed outletResult
BOD≤ 104.8Within limit
COD≤ 5038.9Within limit
TSS≤ 202Within limit
Total N≤ 108Within limit

Design assumptions

  • Raw inlet BOD 250 mg/L
  • Raw inlet COD 500 mg/L
  • Raw inlet TSS 250 mg/L
  • Raw inlet TKN 40 mg/L
  • Raw inlet oil and grease 30 mg/L
  • Design temperature 15–32 °C
  • Checked against: NGT 2019 (O.A. 1069/2018)
  • Plant running 16 hours a day
  • Inlet quality: typical domestic sewage (CPHEEO 2013), no lab report; COD = 2 x BOD

Design checks

  • screen type: a channel bar screen reaches only 0.21 m/s at a buildable width: basket screen (10 mm) in a 1 x 1 m inlet chamber instead

Engineering notes

Points our engineers confirm during detailed design:

  • SADp (scour air per permeate): 30.7 is outside ..30 Nm3/m3

Budget

Typical market range (published figures, 2026) — not an NBW quotation

CAPEX, turnkey plant. ±30%. Excludes GST, land, civil building and site work.
CapacitySTP — MBR
50 KLD₹35 L – ₹50 L
Running cost (O&M) per KL treated: power, chemicals, manpower, sludge and AMC/membranes. Typical market range (published figures, 2026) — not an NBW quotation.
CapacitySTP — MBR
50 KLD₹22 – 38 per KL

These are published market figures, not Navbharat Water's prices. For our own estimate for your project, request a quote.

What quotes often exclude

  • GST
  • Land and civil building / shed
  • Site work: excavation, piling, dewatering
  • Power connection up to the plant panel
  • Consent (CTE / CTO) fees and liaison
  • Operation and maintenance after commissioning

Check your SPCB consent

The State Pollution Control Board consent (CTE / CTO) for your project sets the outlet limits the plant must meet, which can be stricter than the national norm. Check it before you finalise the design: STP discharge norms explained.

Frequently asked questions

What size of tanks does a 50 KLD MBR STP need?

About 64 m3 of tanks in all: oil and grease trap 0.7 m3; equalisation tank 25 m3; mbr aerobic / membrane tank (flat sheet) 12.6 m3; mbr anoxic tank 3.2 m3; chlorine contact tank 1.6 m3; treated water tank 16.9 m3; sludge holding tank 4.4 m3.

How much space and power does a 50 KLD MBR STP need?

A plot about 12.9 x 14.1 m including the equipment room; 15.2 kW connected, 8.2 kW running, about 125 kWh a day (2.5 kWh per m3) at 16 h a day.

Does a 50 KLD MBR STP meet NGT 2019?

Computed outlet BOD 4.8, TSS 2 mg/L against NGT 2019 BOD 10, COD 50, TSS 20 mg/L: within the limits.

Related

Preliminary estimate, not for construction. Detailed design and quotation by NBW engineers.